A1(M) Wentbridge Viaduct Yorkshire roadworks: Bridge closure between Leeds and Doncaster to be extended by eight months after defects found
Work on resurfacing, renewing and waterproofing the Grade II-listed bridge between Leeds and Doncaster began at Easter and was due to finish this month.
However, National Highways has now confirmed that the deadline has been pushed back to April 2024 due to ‘unforeseen issues’.
Advertisement
Hide AdAdvertisement
Hide AdDelays have built up in the area due to the contraflow system that has been in place.
The problems discovered, as reported by The New Civil Engineer, include a loss of concrete on the deck ends, defects to safety barrier foundations and damage to the maintenance walkway anchor points.
There are also improvements scheduled for the nearby Wentedge Bridge.
The viaduct was built in 1961 to carry the A1 over the River Went and is one of the largest structures of its kind in Europe.
National Highways added that the defects identified do not pose a safety risk.